Projection Explanation: Limerick 2
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
728.0 |
-38.31 days |
| Containment Type |
BWR-MARK 2 |
+20.33 days |
| Reactor Type (NSSS) |
GE 4 |
+7.12 days |
| State |
PA |
+3.16 days |
| Units at Site |
2.0 |
-1.75 days |
| Prior Cycle Length (months) |
23.9 |
+1.2 days |
| Age at Outage (years) |
37.3 |
+1.05 days |
| Net Capacity (MWe) |
1122.0 |
-0.95 days |
| unit_pct_in_predicted_month |
0.5 |
+0.82 days |
| Outage Number (experience) |
14.0 |
-0.76 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?