Prediction Explanation: Oconee 3
Feature importance and per-unit prediction explanations for the model.
Per-Unit Prediction Explanation
Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
732.0 |
-34.62 days |
| Reactor Type (NSSS) |
B&W LLP |
+17.62 days |
| State |
SC |
+5.21 days |
| Age at Outage (years) |
53.4 |
-4.96 days |
| Prior Cycle Length (months) |
24.1 |
+4.43 days |
| Containment Type |
PWR-DRYAMB |
-4.18 days |
| Balancing Authority |
DUK |
+3.05 days |
| cycle_interval_cv |
0.1 |
+1.35 days |
| Net Capacity (MWe) |
859.0 |
+1.16 days |
| 3-Outage Rolling Avg Duration |
18.7 |
+1.12 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?