Prediction Explanation: Vogtle 2

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 543.0 +17.32 days
Containment Type PWR-DRYAMB -7.79 days
Reactor Type (NSSS) WEST 4LP -6.04 days
Prior Cycle Length (months) 17.9 -2.74 days
State GA -1.79 days
Years to License Expiration 22.4 -1.48 days
Net Capacity (MWe) 1152.0 -1.07 days
Age at Outage (years) 37.3 +1.05 days
Units at Site 4.0 -1.01 days
Fleet Outages This Year 2.0 +0.7 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?