Reactor Status Timeline
Online NRC data, Mon to Fri ? Actual daily reactor status from NRC reports (Mon to Fri) and the current state. What is coming -- the utility's published Scheduled outage and NukeWorker's model Projection -- is part of a subscription. Colored by status. How far ahead you can see depends on your plan.OnlineReduced PowerCoastdownPower AscensionRefueling OutageScram⚡Scram (reactor trip)
?
Composite Operational Excellence Score (0-100) — average percentile rank across 7 dimensions in three sub-scores: Reliability (capacity factor, forced outage days, B2B avg streak), Efficiency (fuel utilization, refuel duration), and Discipline (startup duration, scram count). 5-year window. Higher = more operationally excellent. Click to see the full breakdown.
Excellence
ranked of 93
Subscribers
?
Days of continuous operation since the last outage ended. Clean run (no forced outages since last refueling).
106
Current Run
days ✔
?
Longest recorded period of continuous operation between outages (2008-04-18 to 2009-10-08).
538
Record Run
days
?
Breaker-to-Breaker runs — continuous operation exceeding the cycle-adjusted threshold set for this unit with no trips to 0% power.
8
B2B Runs
?
Lifetime capacity factor: average power level across all recorded days (100% = always at full power).
92.1%
Capacity Factor
?
Net electricity actually generated over the most recent 12 months reported by the U.S. EIA (Form EIA-923), summed across every unit at this plant. Authoritative actuals, not an estimate.
20.02 TWh
Net Generation
EIA-923 · 12 mo to 2026-06 · plant total
?
Total number of scheduled refueling outages detected in the historical data.
19
Outages
since 1999
?
Average time from first power generation (>0%) to sustained full power (≥95% for 2+ days) across the last 3 scheduled outages. Click to compare against the fleet on the Operator Efficiency Leaderboard.
2.7
Avg Startup
days (last 3)
?
Average fuel utilization — percent of the designed fuel cycle that this unit consumes before refueling, derived from the historical burn-down trajectory. Higher = more efficient operator (refuels with less margin remaining; closer to coastdown). Computed as 100% minus the unit's average refuel-point fuel %, using the last 3 years where available, otherwise lifetime average. Click to compare against the fleet on the Operator Efficiency Leaderboard.
97.9%
Fuel Utilization
3yr avg
?
NukeWorker's Operational Excellence Score is a composite 0–100 ranking of every active US nuclear unit across 7 measured performance metrics, grouped into three sub-scores:
• Reliability — capacity factor, forced outage days, B2B avg streak
• Efficiency — fuel utilization, refuel duration
• Discipline — startup duration, scram count
Each unit's metric is converted to a percentile across the active fleet. Sub-score = average of its components; composite = average of the three sub-scores. Use the time-window toggle below to switch between 3yr / 5yr / lifetime.
• Reliability — capacity factor, forced outage days, B2B avg streak
• Efficiency — fuel utilization, refuel duration
• Discipline — startup duration, scram count
Each unit's metric is converted to a percentile across the active fleet. Sub-score = average of its components; composite = average of the three sub-scores. Use the time-window toggle below to switch between 3yr / 5yr / lifetime.
Time window
— change how far back we look
5-yr trend:
↑ +5.4 pts vs 2025
Compare Comanche Peak 2 head-to-head with up to 3 other units.
Compare now
?
Duration of each outage in days, shown chronologically. Green bars are scheduled refueling outages, red bars are forced/unscheduled. The orange dashed line marks the average duration. Extended outages (>180 days) and D&D periods are excluded.
Outage Duration Trend
Comanche Peak 2 has 40 outages plotted here, averaging 18 days each. The most recent, in May 2026, was a scheduled refueling outage lasting 25 days.
?
Time in days from first power generation (>0%) to sustained full power (≥95% for 2+ consecutive days) after each scheduled refueling outage. The dashed line marks the average. Includes startup testing holds and power dips.
Startup Duration Trend
After a refueling outage, Comanche Peak 2 takes about 5 days to climb from first power back to full power. That average is drawn from 19 startups on record, and the most recent took 2 days.
?
Estimated fuel remaining in the current cycle, expressed as a percentage of the unit's typical cycle. Starts at 100% when the unit returns to power post-refuel and drops as full-power-days are burned. Days at reduced power burn fuel proportionally — so a unit with significant downtime (high burn deficit) drops slower and ends up with MORE fuel left than its calendar position would suggest. Coastdown threshold around 15%. Toggle to overlay past cycles on a normalized "days into cycle" axis to see how aggressively this unit historically burns down before refuel.
Fuel Burn Down Cycle since May 29, 2026
80.2% remaining
0.5 FPD margin
Comanche Peak 2 has an estimated 80.2% of its fuel left. Across its last 18 cycles, it has refueled with an average of 3.3% remaining.
Avg refuel: 3.3%
Avg refuel (3yr): 2.1%
Deepest burn: 0.0% (2005-04 → 2006-10)
Most margin: 13.8% (2019-01 → 2020-04)
?
Monthly capacity factor with outage events overlaid as red bands. Green bars show average power level per month. Toggle to Daily view for raw daily data.
Power History
Over its operating life, Comanche Peak 2 has run at about 92.1% of its rated capacity. Across the last 12 reported months it averaged 92.8%. On the chart, flat stretches near the top are full-power running and drops to zero are outages.
This table logs every recorded outage for Comanche Peak 2, 40 in all since 1999. Of those, 19 were scheduled refueling outages and 21 were unplanned or forced. The typical outage lasted about 18 days. Where the Scheduled column shows (Model), the date is a NukeWorker projection because the utility had not published one.
| Type ⇅ | Actual Start ⇅ | Actual End ⇅ | Duration ⇅ | Days Online ⇅ | Scheduled | Delta |
|---|---|---|---|---|---|---|
|
Scheduled
2RF22
|
2026-05-04 | 2026-05-28 | 25 | 229d | 2026-04-18 | +16d |
|
Scram
# 57929
|
2025-09-15 | 2025-09-17 | 3 | 300d | - | - |
|
Scheduled
2RF21
|
2024-10-21 | 2024-11-19 | 30 | 214d | 2024-10-14 | +7d |
|
Scram
# 57033
|
2024-03-18 | 2024-03-21 | 4 | 4d | - | - |
|
Scram
# 57024
|
2024-03-13 | 2024-03-14 | 2 | 292d | - | - |
|
Scheduled
2RF20
|
2023-04-24 | 2023-05-26 | 33 | 526d | 2023-04-23 | +1d |
|
Scheduled
2RF19
|
2021-10-04 | 2021-11-14 | 42 | 108d | 2021-10-18 | -14d |
|
Scram
# 55295
|
2021-06-08 | 2021-06-18 | 11 | 392d | - | - |
|
Scheduled
2RF18
|
2020-04-20 | 2020-05-12 | 23 | 109d | 2020-04-19 | +1d |
|
Scram
# 54460
|
2020-01-02 | 2020-01-02 | 1 | 349d | - | - |
|
Unscheduled
|
2019-01-16 | 2019-01-18 | 3 | 2d | - | - |
|
Scheduled
2RF17
|
2018-12-09 | 2019-01-14 | 37 | 116d | 2018-09-26 | +74d |
|
Scram
# 53550
|
2018-08-14 | 2018-08-15 | 2 | 258d | - | - |
|
Scram
# 53091
|
2017-11-26 | 2017-11-29 | 4 | 83d | - | - |
|
Scram
# 52945
|
2017-09-02 | 2017-09-04 | 3 | 23d | - | - |
|
Unscheduled
|
2017-06-06 | 2017-08-10 | 66 | 32d | - | - |
|
Scheduled
2RF16
|
2017-04-03 | 2017-05-05 | 33 | 509d | 2017-04-01 | +2d |
| 2015-10-04 | 2015-11-11 | 39 | 526d | 2015-09-15 | +19d | |
|
Scheduled
2RF14
|
2014-03-30 | 2014-04-26 | 28 | 147d | 2014-03-29 | +1d |
|
Scram
# 49497
|
2013-11-02 | 2013-11-03 | 2 | 366d | - | - |
|
Scheduled
2RF13
|
2012-10-07 | 2012-11-01 | 26 | 186d | 2012-10-01 | +6d |
|
Unscheduled
|
2012-04-02 | 2012-04-04 | 3 | 316d | - | - |
|
Scram
# 46863
|
2011-05-20 | 2011-05-22 | 3 | 25d | - | - |
|
Scheduled
2RF12
|
2011-04-03 | 2011-04-25 | 23 | 518d | 2011-04-02 | +1d |
|
Unscheduled
Startup Hold
|
2009-10-31 | 2009-11-01 | 2 | 2d | - | - |
|
Scheduled
2RF11
|
2009-10-08 | 2009-10-29 | 22 | 538d | 2009-10-03 | +5d |
|
Scheduled
2RF10
|
2008-03-30 | 2008-04-18 | 20 | 13d | 2008-03-29 | +1d |
|
Unscheduled
|
2008-03-17 | 2008-03-17 | 1 | 504d | - | - |
|
Unscheduled
Startup Hold
|
2006-10-30 | 2006-10-30 | 1 | 5d | - | - |
|
Scheduled
2RF9
|
2006-10-08 | 2006-10-25 | 18 | 529d | 2006-10-07 | +1d |
|
Scheduled
2RF8
|
2005-03-27 | 2005-04-27 | 32 | 458d | 2005-03-26 | +1d |
|
Unscheduled
|
2003-12-23 | 2003-12-25 | 3 | 56d | - | - |
|
Scheduled
2RF7
|
2003-10-05 | 2003-10-28 | 24 | 72d | 2003-10-05 | 0d |
|
Unscheduled
|
2003-07-09 | 2003-07-25 | 17 | 42d | - | - |
|
Unscheduled
|
2003-05-15 | 2003-05-28 | 14 | 342d | - | - |
|
Unscheduled
|
2002-06-07 | 2002-06-07 | 1 | 35d | - | - |
|
Scheduled
2RF6
|
2002-03-31 | 2002-05-03 | 34 | 512d | 2002-03-31 | 0d |
|
Scheduled
2RF5
|
2000-10-01 | 2000-11-04 | 35 | 529d | 2000-10-01 | 0d |
|
Scheduled
2RF4
|
1999-03-20 | 1999-04-21 | 33 | 75d | 1999-03-20 | 0d |
|
Unscheduled
|
1999-01-04 | 1999-01-04 | 1 | - | - | - |
Page created in 0.067 seconds with 13 queries.