Farley 1 - Status & History

Comprehensive reactor performance metrics, cycle analysis, and historical outage data.

Reactor Status Timeline

Online NRC data, Mon to Fri ? Actual daily reactor status from NRC reports (Mon to Fri) and the current state. What is coming -- the utility's published Scheduled outage and NukeWorker's model Projection -- is part of a subscription. Colored by status. How far ahead you can see depends on your plan.
Oct2025NovDecJan2026FebMarAprMayJunJulAugSepCoastdown: Sep 12, 2025 to Sep 28, 2025Refueling Outage (1R33): Sep 29, 2025 to Oct 24, 20251R33Power Ascension: Oct 25, 2025 to Oct 28, 2025Forced Outage: Oct 29, 2025Power Ascension: Oct 30, 2025 to Nov 1, 2025Online: Nov 2, 2025 to Sep 12, 2026Today
OnlineCoastdownPower AscensionRefueling OutageForced Outage
?
Composite Operational Excellence Score (0-100) — average percentile rank across 7 dimensions in three sub-scores: Reliability (capacity factor, forced outage days, B2B avg streak), Efficiency (fuel utilization, refuel duration), and Discipline (startup duration, scram count). 5-year window. Higher = more operationally excellent. Click to see the full breakdown.
   
Excellence
ranked of 93
Subscribers
?
Days of continuous operation since the last outage ended. Clean run (no forced outages since last refueling).
318
Current Run
days ✔
?
Longest recorded period of continuous operation between outages (2009-05-06 to 2010-10-11).
523
Record Run
days
?
Breaker-to-Breaker runs — continuous operation exceeding the cycle-adjusted threshold set for this unit with no trips to 0% power.
6
B2B Runs
?
Lifetime capacity factor: average power level across all recorded days (100% = always at full power).
90.7%
Capacity Factor
?
Net electricity actually generated over the most recent 12 months reported by the U.S. EIA (Form EIA-923), summed across every unit at this plant. Authoritative actuals, not an estimate.
15.11 TWh
Net Generation
EIA-923 · 12 mo to 2026-06 · plant total
?
Total number of scheduled refueling outages detected in the historical data.
18
Outages
since 1999
?
Average time from first power generation (>0%) to sustained full power (≥95% for 2+ days) across the last 3 scheduled outages. Click to compare against the fleet on the Operator Efficiency Leaderboard.
5.7
Avg Startup
days (last 3)
?
Average fuel utilization — percent of the designed fuel cycle that this unit consumes before refueling, derived from the historical burn-down trajectory. Higher = more efficient operator (refuels with less margin remaining; closer to coastdown). Computed as 100% minus the unit's average refuel-point fuel %, using the last 3 years where available, otherwise lifetime average. Click to compare against the fleet on the Operator Efficiency Leaderboard.
99.3%
Fuel Utilization
3yr avg
?
NukeWorker's Operational Excellence Score is a composite 0–100 ranking of every active US nuclear unit across 7 measured performance metrics, grouped into three sub-scores:
Reliability — capacity factor, forced outage days, B2B avg streak
Efficiency — fuel utilization, refuel duration
Discipline — startup duration, scram count
Each unit's metric is converted to a percentile across the active fleet. Sub-score = average of its components; composite = average of the three sub-scores. Use the time-window toggle below to switch between 3yr / 5yr / lifetime.
Time window — change how far back we look
5-yr trend: 2021: 61/100 (#32/93)2022: 51/100 (#49/92)2023: 45/100 (#53/92)2024: 43/100 (#61/92)2025: 50/100 (#45/92)2026: 52/100 (#37/93) Stable vs 2025
Compare Farley 1 head-to-head with up to 3 other units. Compare now
?
Duration of each outage in days, shown chronologically. Green bars are scheduled refueling outages, red bars are forced/unscheduled. The orange dashed line marks the average duration. Extended outages (>180 days) and D&D periods are excluded.

Outage Duration Trend

Farley 1 has 42 outages plotted here, averaging 19 days each. The most recent, in Oct 2025, was a unplanned outage lasting 1 day.
?
Time in days from first power generation (>0%) to sustained full power (≥95% for 2+ consecutive days) after each scheduled refueling outage. The dashed line marks the average. Includes startup testing holds and power dips.

Startup Duration Trend

After a refueling outage, Farley 1 takes about 6 days to climb from first power back to full power. That average is drawn from 18 startups on record, and the most recent took 8 days.
?
Estimated fuel remaining in the current cycle, expressed as a percentage of the unit's typical cycle. Starts at 100% when the unit returns to power post-refuel and drops as full-power-days are burned. Days at reduced power burn fuel proportionally — so a unit with significant downtime (high burn deficit) drops slower and ends up with MORE fuel left than its calendar position would suggest. Coastdown threshold around 15%. Toggle to overlay past cycles on a normalized "days into cycle" axis to see how aggressively this unit historically burns down before refuel.

Fuel Burn Down Cycle since Oct 29, 2025

37.6% remaining 1.7 FPD margin
Farley 1 has an estimated 37.6% of its fuel left. Across its last 17 cycles, it has refueled with an average of 2.1% remaining.
Avg refuel: 2.1% Avg refuel (3yr): 0.7% Deepest burn: 0.0% (2003-05 → 2004-10) Most margin: 8.0% (2022-12 → 2024-04)
?
Monthly capacity factor with outage events overlaid as red bands. Green bars show average power level per month. Toggle to Daily view for raw daily data.

Power History

Over its operating life, Farley 1 has run at about 90.7% of its rated capacity. Across the last 12 reported months it averaged 91.9%. On the chart, flat stretches near the top are full-power running and drops to zero are outages.
This table logs every recorded outage for Farley 1, 42 in all since 1999. Of those, 18 were scheduled refueling outages and 24 were unplanned or forced. The typical outage lasted about 19 days. Where the Scheduled column shows (Model), the date is a NukeWorker projection because the utility had not published one.
Unscheduled Startup Hold
2025-10-29 2025-10-29 1 5d - -
Scheduled 1R33
2025-09-29 2025-10-24 26 508d 2025-09-17 +12d
Scheduled 1R32
2024-04-08 2024-05-09 32 429d 2024-04-05 +3d
Scram # 56329
2023-02-02 2023-02-04 3 43d - -
Scheduled 1R31SGR/Major
2022-09-19 2022-12-21 94 45d 2022-09-18 +1d
Scram # 56028
2022-08-04 2022-08-05 2 468d - -
Scram # 55206
2021-04-23 2021-04-23 1 6d - -
Scheduled 1R30
2021-03-22 2021-04-17 27 516d 2021-03-22 0d
Scheduled 1R29
2019-09-30 2019-10-23 24 217d 2019-09-29 +1d
Unscheduled
2019-02-20 2019-02-25 6 145d - -
Unscheduled
2018-09-25 2018-09-28 4 138d - -
Scheduled 1R28
2018-04-09 2018-05-10 32 8d 2018-04-01 +8d
Unscheduled
2018-03-27 2018-04-01 6 484d - -
Scram # 52395
2016-11-27 2016-11-28 2 9d - -
Unscheduled
2016-11-18 2016-11-18 1 5d - -
Scram # 52356
2016-11-09 2016-11-13 5 4d - -
Scheduled # 52274 1R27
2016-10-02 2016-11-05 35 491d 2016-09-24 +8d
Unscheduled
2015-05-27 2015-05-30 4 19d - -
Unscheduled
2015-05-08 2015-05-08 1 4d - -
Scheduled 1R26
2015-03-30 2015-05-04 36 521d 2015-03-29 +1d
Scheduled 1R25
2013-09-30 2013-10-25 26 109d 2013-10-06 -6d
Scram # 49106
2013-06-12 2013-06-13 2 318d - -
Unscheduled
2012-07-27 2012-07-29 3 93d - -
Scheduled 1R24
2012-04-02 2012-04-25 24 73d 2012-03-25 +8d
Unscheduled
2012-01-17 2012-01-20 4 425d - -
Scheduled 1R23
2010-10-11 2010-11-18 39 523d 2010-10-02 +9d
Scheduled 1R22
2009-04-03 2009-05-06 34 134d 2009-03-28 +6d
Unscheduled
2008-11-20 2008-11-20 1 114d - -
Unscheduled
2008-07-23 2008-07-29 7 254d - -
Scheduled 1R21
2007-09-29 2007-11-12 45 455d 2007-09-29 0d
Unscheduled
2006-07-01 2006-07-01 1 39d - -
Scheduled 1R20
2006-04-08 2006-05-23 46 292d 2006-04-07 +1d
Unscheduled
2005-06-19 2005-06-20 2 216d - -
Scheduled 1R19
2004-10-02 2004-11-15 45 214d 2004-10-01 +1d
Unscheduled
2004-03-02 2004-03-02 1 307d - -
Scheduled 1R18
2003-03-29 2003-04-30 33 108d 2003-03-29 0d
Unscheduled
2002-12-11 2002-12-11 1 55d - -
Unscheduled
2002-10-16 2002-10-17 2 165d - -
Unscheduled
2002-05-04 2002-05-04 1 171d - -
Scheduled 1R17
2001-10-06 2001-11-14 40 500d 2001-10-06 0d
Scheduled 1R16SGR/Major
2000-03-04 2000-05-24 82 281d 2000-03-04 0d
Unscheduled
1999-05-28 1999-05-28 1 - - -