San Onofre 2

Decommissioned

Southern California Edison·San Clemente, CA·PWR·1,070 MWe

Data refreshed 7.9h ago Rx Status: Jul 24, 2013 (M-F)

Decommissioned

Permanently shut down on 2012-01-09. Outage statistics below reflect only the operating period. The final shutdown is not counted as an outage.

Outage Record

Outage Days by Year

?
Total days spent in outage each year, split by scheduled refueling (blue) and forced/unplanned (red). Lower totals indicate better reliability and outage execution. Hover for details.
Across its recorded history, San Onofre 2 has spent 208 days in scheduled refueling outages and 255 days in forced or unplanned outages. Taller bars mark the years with the most downtime.
?
Duration of each outage in days, shown chronologically. Green bars are scheduled refueling outages, red bars are forced/unscheduled. The orange dashed line marks the average duration. Extended outages (>180 days) and D&D periods are excluded.

Outage Duration Trend

San Onofre 2 has 24 outages plotted here, averaging 19 days each. The most recent, in Sep 2011, was a unplanned outage lasting 2 days.
?
Scheduled refueling outage durations over time. Green bars are at or below this unit's average, amber up to 30% above it, red beyond that. The dashed line is the average. Shorter outages mean better execution.

Refueling Duration Trend

San Onofre 2 has completed 3 scheduled refueling outages on record, averaging 69 days each. The most recent, in Nov 2007, ran 53 days.
?
Time in days from first power generation (>0%) to sustained full power (≥95% for 2+ consecutive days) after each scheduled refueling outage. The dashed line marks the average. Includes startup testing holds and power dips.

Startup Duration Trend

After a refueling outage, San Onofre 2 takes about 9 days to climb from first power back to full power. That average is drawn from 4 startups on record, and the most recent took 8 days.
?
Daily reactor power over the 120 days before each scheduled refueling outage, one line per refueling, lined up on the day the outage began. A coastdown is the slow decline as the fuel runs out near the end of a cycle. The highlighted line is the most recent refueling and fainter lines are older. Counts and medians cover coastdowns of a week or longer. A shutdown straight from full power, with no decline ahead of it, is what a forced outage looks like.

Coastdown Before Refueling

2 of 4 refuelings 12 days median 93% power at shutdown 0.7% per day
San Onofre 2 coasted down for a week or longer before 2 of its 4 refuelings on record. Those coastdowns ran a median of 12 days and ended near 93% power. The most recent refueling, in Sep 2009, began with no extended coastdown.
?
Monthly capacity factor with outage events overlaid as red bands. Green bars show average power level per month. Toggle to Daily view for raw daily data.

Power History

Over its operating life, San Onofre 2 has run at about 75.5% of its rated capacity. Across the last 12 reported months it averaged 0.0%. On the chart, green stretches near the top are full-power running, amber marks reduced power (50 to 89%), and red drops toward zero are outages.

Outage History & Daily Power Log

This table logs every recorded outage for San Onofre 2, 26 in all since 1999. Of those, 5 were scheduled refueling outages and 21 were unplanned or forced. The typical outage lasted about 47 days. Where the Scheduled column shows (Model), the date is a NukeWorker projection because the utility had not published one.
Scheduled 2R17Ext. Shutdown
2012-01-10 Decommissioned 1 (D&D) 122d 2012-01-10 0d
Scram # 47252 Auto
2011-09-09 2011-09-10 2 518d - -
Scheduled 2R16SGR/Major
2009-09-27 2010-04-09 195 11d 2009-09-27 0d
Unscheduled
2009-09-14 2009-09-16 3 208d - -
Unscheduled
2008-12-28 2009-02-18 53 202d - -
Unscheduled
2008-06-06 2008-06-09 4 4d - -
Unscheduled
2008-06-02 2008-06-02 1 136d - -
Scheduled 2R15
2007-11-27 2008-01-18 53 32d 2007-11-26 +1d
Unscheduled
2007-10-22 2007-10-26 5 116d - -
Unscheduled
2007-06-21 2007-06-28 8 4d - -
Unscheduled
2007-06-16 2007-06-17 2 428d - -
Scheduled 2R14
2006-01-04 2006-04-14 101 261d 2006-01-03 +1d
Unscheduled
2005-04-18 2005-04-18 1 42d - -
Unscheduled
2005-02-16 2005-03-07 20 10d - -
Unscheduled
2005-02-04 2005-02-06 3 76d - -
Unscheduled
2004-11-20 2004-11-20 1 223d - -
Unscheduled
2004-04-11 2004-04-11 1 8d - -
Scheduled 2R13
2004-02-10 2004-04-03 54 232d 2004-02-09 +1d
Unscheduled
2003-06-22 2003-06-23 2 140d - -
Unscheduled
2003-02-02 2003-02-02 1 88d - -
Unscheduled
2002-11-03 2002-11-06 4 125d - -
Unscheduled
2002-07-01 2002-07-01 1 2d - -
Unscheduled
2002-05-21 2002-06-29 40 211d - -
Unscheduled
2001-10-14 2001-10-22 9 332d - -
Unscheduled
2000-10-08 2000-11-16 40 591d - -
Unscheduled
1999-01-03 1999-02-25 54 - - -