Watts Bar 1

Online · 100% power

Tennessee Valley Authority·Spring City, TN·PWR·1,123 MWe

Data refreshed 13.8h ago Rx Status: Oct 23, 2026 at 5:36 AM (M-F)

Reactor Status Timeline

Online NRC data, Mon to Fri ? Actual daily reactor status from NRC reports (Mon to Fri) and the current state. What is coming -- the utility's published Scheduled outage and NukeWorker's model Projection -- is part of a subscription. Colored by status. How far ahead you can see depends on your plan.
Nov2025DecJan2026FebMarAprMayJunJulAugSepOctNovOnline: Oct 24, 2025 to Apr 17, 2026Refueling Outage (U1R20): Apr 18, 2026 to May 15, 2026U1R20Power Ascension: May 16, 2026 to May 21, 2026Online: May 22, 2026 to Oct 24, 2026Today
OnlinePower AscensionRefueling Outage
?
Composite Operational Excellence Score (0-100) — average percentile rank across 7 dimensions in three sub-scores: Reliability (capacity factor, forced outage days, B2B avg streak), Efficiency (fuel utilization, refuel duration), and Discipline (startup duration, scram count). 5-year window. Higher = more operationally excellent. Click to see the full breakdown.
   
Excellence
Rank locked · 93 units
Subscribers
?
Days of continuous operation since the last outage ended (Started 2026-05-15). Clean run (no forced outages since last refueling).
162
Current Run
days ✔
?
Longest recorded period of continuous operation between outages (1999-04-14 to 2000-09-10).
515
Record Run
days
?
Breaker-to-Breaker runs — continuous operation exceeding the cycle-adjusted threshold set for this unit with no trips to 0% power.
4
B2B Runs
?
Lifetime capacity factor: average power level across all recorded days (100% = always at full power).
88.4%
Capacity Factor
?
Net electricity actually generated over the most recent 12 months reported by the U.S. EIA (Form EIA-923), summed across every unit at this plant. Authoritative actuals, not an estimate.
19.81 TWh
Net Generation
EIA-923 · 12 mo to 2026-07 · plant total
?
Total number of scheduled refueling outages detected in the historical data.
19
Outages
since 1999
?
Average time from first power generation (>0%) to sustained full power (≥95% for 2+ days) across the last 3 scheduled outages. Click to compare against the fleet on the Operator Efficiency Leaderboard.
5.3
Avg Startup
days (last 3)
?
Average fuel utilization — percent of the designed fuel cycle that this unit consumes before refueling, derived from the historical burn-down trajectory. Higher = more efficient operator (refuels with less margin remaining; closer to coastdown). Computed as 100% minus the unit's average refuel-point fuel %, using the last 3 years where available, otherwise lifetime average. Click to compare against the fleet on the Operator Efficiency Leaderboard.
88.0%
Fuel Utilization
3yr avg

Reactor Status

Capacity Factor (365-Day)

?
100%
Current
91.2%
365-Day Avg
#59
of 94 plants
Min: 0% Max: 100% 33 days <80%

Outage Days by Year

?
Total days spent in outage each year, split by scheduled refueling (blue) and forced/unplanned (red). Lower totals indicate better reliability and outage execution. Hover for details.
Across its recorded history, Watts Bar 1 has spent 737 days in scheduled refueling outages and 291 days in forced or unplanned outages. Taller bars mark the years with the most downtime.
?
Duration of each outage in days, shown chronologically. Green bars are scheduled refueling outages, red bars are forced/unscheduled. The orange dashed line marks the average duration. Extended outages (>180 days) and D&D periods are excluded.

Outage Duration Trend

Watts Bar 1 has 53 outages plotted here, averaging 19 days each. The most recent, in Apr 2026, was a scheduled refueling outage lasting 28 days.
?
Scheduled refueling outage durations over time. Green bars are at or below this unit's average, amber up to 30% above it, red beyond that. The dashed line is the average. Shorter outages mean better execution.

Refueling Duration Trend

Watts Bar 1 has completed 19 scheduled refueling outages on record, averaging 39 days each. The most recent, in Apr 2026, ran 28 days.
?
Time in days from first power generation (>0%) to sustained full power (≥95% for 2+ consecutive days) after each scheduled refueling outage. The dashed line marks the average. Includes startup testing holds and power dips.

Startup Duration Trend

After a refueling outage, Watts Bar 1 takes about 6 days to climb from first power back to full power. That average is drawn from 19 startups on record, and the most recent took 5 days.
?
Daily reactor power over the 120 days before each scheduled refueling outage, one line per refueling, lined up on the day the outage began. A coastdown is the slow decline as the fuel runs out near the end of a cycle. The highlighted line is the most recent refueling and fainter lines are older. Counts and medians cover coastdowns of a week or longer. A shutdown straight from full power, with no decline ahead of it, is what a forced outage looks like.

Coastdown Before Refueling

5 of 19 refuelings 28 days median 81% power at shutdown 0.6% per day
Watts Bar 1 coasted down for a week or longer before 5 of its 19 refuelings on record. Those coastdowns ran a median of 28 days and ended near 81% power. The most recent refueling, in Apr 2026, began with no extended coastdown.
?
Estimated fuel remaining in the current cycle, expressed as a percentage of the unit's typical cycle. Starts at 100% when the unit returns to power post-refuel and drops as full-power-days are burned. Days at reduced power burn fuel proportionally — so a unit with significant downtime (high burn deficit) drops slower and ends up with MORE fuel left than its calendar position would suggest. Coastdown threshold around 15%. Toggle to overlay past cycles on a normalized "days into cycle" axis to see how aggressively this unit historically burns down before refuel.

Fuel Burn Down Cycle since May 19, 2026

68.4% remaining 0.5 FPD margin
Watts Bar 1 has an estimated 68.4% of its fuel left. Across its last 18 cycles, it has refueled with an average of 3.0% remaining.
Avg refuel: 3.0% Avg refuel (3yr): 12.0% Deepest burn: 0.0% (1999-04 → 2000-09) Most margin: 24.0% (2024-12 → 2026-04)
?
Monthly capacity factor with outage events overlaid as red bands. Green bars show average power level per month. Toggle to Daily view for raw daily data.

Power History

Over its operating life, Watts Bar 1 has run at about 88.4% of its rated capacity. Across the last 12 reported months it averaged 91.2%. On the chart, green stretches near the top are full-power running, amber marks reduced power (50 to 89%), and red drops toward zero are outages.

Outage History & Daily Power Log

This table logs every recorded outage for Watts Bar 1, 53 in all since 1999. Of those, 19 were scheduled refueling outages and 34 were unplanned or forced. The typical outage lasted about 19 days. Where the Scheduled column shows (Model), the date is a NukeWorker projection because the utility had not published one.
Scheduled U1R20
2026-04-18 2026-05-15 28 348d 2026-04-17 +1d
Scram # 57500 Auto
2025-01-17 2025-05-05 109 39d - -
Scheduled U1R19
2024-11-02 2024-12-09 38 106d 2024-10-12 +21d
Scram # 57214 Auto
2024-07-09 2024-07-19 11 43d - -
Unscheduled
2024-05-25 2024-05-27 3 380d - -
Scheduled U1R18
2023-04-15 2023-05-11 27 498d 2023-04-14 +1d
Scheduled U1R17
2021-10-30 2021-12-03 35 514d 2021-10-29 +1d
Scheduled U1R16
2020-05-09 2020-06-03 26 79d 2020-03-10 +60d
Scram # 54532 Manual
2020-02-20 2020-02-20 1 121d - -
Unscheduled
2019-09-16 2019-10-22 37 5d - -
Unscheduled
2019-09-05 2019-09-11 7 3d - -
Scram # 54252 Manual
2019-09-01 2019-09-02 2 306d - -
Scram # 53697 Manual
2018-10-28 2018-10-30 3 2d - -
Scheduled U1R15
2018-09-15 2018-10-26 42 495d 2018-09-08 +7d
Scram # 52732 Manual
2017-05-05 2017-05-08 4 2d - -
Scram # 52732 Manual
2017-05-03 2017-05-03 1 3d - -
Scheduled U1R14
2017-03-19 2017-04-30 43 359d 2017-03-20 -1d
Scram # 51815 Auto
2016-03-23 2016-03-25 3 131d - -
Unscheduled
2015-11-07 2015-11-13 7 17d - -
Scheduled U1R13
2015-09-21 2015-10-21 31 204d 2015-09-14 +7d
Scram # 50839 Manual
2015-02-22 2015-03-01 8 222d - -
Scram # 50278 Manual
2014-07-14 2014-07-15 2 74d - -
Scheduled U1R12
2014-03-24 2014-05-01 39 267d 2014-04-07 -14d
Scram # 49154 Auto
2013-06-29 2013-06-30 2 244d - -
Scheduled U1R11
2012-09-10 2012-10-28 49 12d 2012-09-10 0d
Scram # 48238 Auto
2012-08-28 2012-08-29 2 319d - -
Unscheduled
2011-10-08 2011-10-14 7 132d - -
Scram # 46902 Auto
2011-05-29 2011-05-29 1 9d - -
Scheduled U1R10
2011-04-04 2011-05-20 47 138d 2011-03-20 +15d
Unscheduled
2010-11-15 2010-11-17 3 175d - -
Unscheduled
2010-05-22 2010-05-24 3 214d - -
Scheduled U1R9
2009-09-21 2009-10-20 30 362d 2009-09-20 +1d
Unscheduled
2008-09-21 2008-09-24 4 38d - -
Unscheduled
2008-08-07 2008-08-14 8 75d - -
Unscheduled
2008-05-18 2008-05-24 7 55d - -
Scheduled U1R8
2008-02-11 2008-03-24 43 438d 2008-02-10 +1d
Scheduled U1R7SGR/Major
2006-09-11 2006-11-30 81 38d 2006-09-10 +1d
Unscheduled
2006-08-01 2006-08-04 4 38d - -
Unscheduled
2006-05-31 2006-06-24 25 426d - -
Scheduled U1R6
2005-02-22 2005-03-31 38 155d 2005-02-21 +1d
Unscheduled
2004-09-20 2004-09-20 1 247d - -
Unscheduled
2004-01-17 2004-01-17 1 89d - -
Scheduled U1R5
2003-09-08 2003-10-20 43 13d 2003-09-08 0d
Unscheduled
2003-08-26 2003-08-26 1 164d - -
Unscheduled
2003-03-10 2003-03-15 6 239d - -
Unscheduled
2002-07-14 2002-07-14 1 67d - -
Unscheduled
2002-05-04 2002-05-08 5 46d - -
Scheduled U1R4
2002-02-25 2002-03-19 23 67d 2002-02-25 0d
Unscheduled
2001-12-20 2001-12-20 1 106d - -
Unscheduled
2001-09-05 2001-09-05 1 58d - -
Unscheduled
2001-06-30 2001-07-09 10 267d - -
Scheduled U1R3
2000-09-10 2000-10-06 27 515d 2000-09-10 0d
Scheduled U1R2
1999-02-27 1999-04-14 47 - 1999-02-27 0d