Projection Explanation: Fermi 2

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 730.0 -44.77 days
Containment Type BWR-MARK 1 +28.05 days
Reactor Type (NSSS) GE 4 +4.17 days
Avg Outages Between Major Maint. 2.0 -3.91 days
Prior Cycle Length (months) 24.0 +3.9 days
Units at Site 1.0 +2.95 days
State MI +2.3 days
Years to License Expiration 17.0 -1.24 days
recent_cycle_anomaly 1.0 -1.1 days
Balancing Authority MISO -0.91 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?