Projection Explanation: Fermi 2
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
730.0 |
-44.77 days |
| Containment Type |
BWR-MARK 1 |
+28.05 days |
| Reactor Type (NSSS) |
GE 4 |
+4.17 days |
| Avg Outages Between Major Maint. |
2.0 |
-3.91 days |
| Prior Cycle Length (months) |
24.0 |
+3.9 days |
| Units at Site |
1.0 |
+2.95 days |
| State |
MI |
+2.3 days |
| Years to License Expiration |
17.0 |
-1.24 days |
| recent_cycle_anomaly |
1.0 |
-1.1 days |
| Balancing Authority |
MISO |
-0.91 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?