Crystal River 3 - Status & History

Comprehensive reactor performance metrics, cycle analysis, and historical outage data.

Decommissioned

Permanently shut down on 2013-02-05. Outage statistics below reflect only the operating period. The final shutdown is not counted as an outage.
?
This unit is permanently shut down (shutdown date: 2013-02-05).
Shut Down
2013-02-05
?
Longest recorded period of continuous operation between outages (2004-09-11 to 2005-10-29).
413
Record Run
days
?
Breaker-to-Breaker runs — continuous operation exceeding the cycle-adjusted threshold (617 days for this 24-month cycle unit) with no trips to 0% power.
0
B2B Runs
?
Lifetime capacity factor: average power level across all recorded days (100% = always at full power).
68.2%
Capacity Factor
?
Total number of scheduled refueling outages detected in the historical data. D&D shutdown period excluded.
5
Outages
since 1999
?
Average time from first power generation (>0%) to sustained full power (≥95% for 2+ days) across the last 3 scheduled outages. Click to compare against the fleet on the Operator Efficiency Leaderboard.
3.7
Avg Startup
days (last 3)
?
Average fuel utilization — percent of the designed fuel cycle that this unit consumes before refueling, derived from the historical burn-down trajectory. Higher = more efficient operator (refuels with less margin remaining; closer to coastdown). Computed as 100% minus the unit's average refuel-point fuel %, using the last 3 years where available, otherwise lifetime average. Click to compare against the fleet on the Operator Efficiency Leaderboard.
95.7%
Fuel Utilization
lifetime avg
?
Duration of each outage in days, shown chronologically. Green bars are scheduled refueling outages, red bars are forced/unscheduled. The orange dashed line marks the average duration. Extended outages (>180 days) and D&D periods are excluded.

Outage Duration Trend

Crystal River 3 has 23 outages plotted here, averaging 11 days each. The most recent, in Aug 2009, was a unplanned outage lasting 1 day.
?
Days between consecutive scheduled refueling outage starts, showing operating cycle regularity. The purple dashed line marks the average cycle length. Most U.S. reactors operate on 18-month (547 day) or 24-month (730 day) cycles.

Cycle Length History

Between refueling outages, Crystal River 3 runs about 739 days, or roughly 24 months, per cycle. That average comes from 4 completed cycles, the most recent lasting 735 days.
?
Time in days from first power generation (>0%) to sustained full power (≥95% for 2+ consecutive days) after each scheduled refueling outage. The dashed line marks the average. Includes startup testing holds and power dips.

Startup Duration Trend

After a refueling outage, Crystal River 3 takes about 4 days to climb from first power back to full power. That average is drawn from 5 startups on record, and the most recent took 2 days.
?
Monthly capacity factor with outage events overlaid as red bands. Green bars show average power level per month. Toggle to Daily view for raw daily data.

Power History

Over its operating life, Crystal River 3 has run at about 68.2% of its rated capacity. Across the last 12 reported months it averaged 0.0%. On the chart, flat stretches near the top are full-power running and drops to zero are outages.
This table logs every recorded outage for Crystal River 3, 24 in all since 1999. Of those, 6 were scheduled refueling outages and 18 were unplanned or forced. The typical outage lasted about 67 days. Where the Scheduled column shows (Model), the date is a NukeWorker projection because the utility had not published one.
Scheduled Ext. Shutdown
2009-09-26 Decommissioned 1228 (D&D) 32d 2009-09-26 0d
Unscheduled
2009-08-25 2009-08-25 1 203d - -
Unscheduled
2009-02-03 2009-02-03 1 6d - -
Unscheduled
2009-01-28 2009-01-28 1 153d - -
Unscheduled
2008-08-25 2008-08-28 4 158d - -
Unscheduled
2008-03-02 2008-03-20 19 87d - -
Scheduled
2007-11-03 2007-12-06 34 254d 2007-11-03 0d
Unscheduled
2007-02-22 2007-02-22 1 183d - -
Unscheduled
2006-08-19 2006-08-23 5 146d - -
Unscheduled
2006-03-18 2006-03-26 9 71d - -
Unscheduled
2005-12-31 2006-01-06 7 22d - -
Scheduled
2005-10-29 2005-12-09 42 413d 2005-10-28 +1d
Unscheduled
2004-09-07 2004-09-11 5 166d - -
Unscheduled
2004-03-24 2004-03-25 2 137d - -
Unscheduled
2003-11-08 2003-11-08 1 2d - -
Unscheduled
2003-11-06 2003-11-06 1 2d - -
Scheduled
2003-10-04 2003-11-04 32 330d 2003-10-04 0d
Unscheduled
2002-11-08 2002-11-08 1 380d - -
Scheduled
2001-09-29 2001-10-24 26 121d 2001-09-29 0d
Unscheduled
2001-05-19 2001-05-31 13 246d - -
Unscheduled
2000-09-10 2000-09-15 6 135d - -
Unscheduled
2000-04-27 2000-04-28 2 151d - -
Unscheduled
1999-11-27 1999-11-28 2 17d - -
Scheduled
1999-10-01 1999-11-10 41 - 1999-10-01 0d