Outage Record

Outage Days by Year

?
Total days spent in outage each year, split by scheduled refueling (blue) and forced/unplanned (red). Lower totals indicate better reliability and outage execution. Hover for details.
Across its recorded history, Crystal River 3 has spent 175 days in scheduled refueling outages and 81 days in forced or unplanned outages. Taller bars mark the years with the most downtime.
?
Duration of each outage in days, shown chronologically. Green bars are scheduled refueling outages, red bars are forced/unscheduled. The orange dashed line marks the average duration. Extended outages (>180 days) and D&D periods are excluded.

Outage Duration Trend

Crystal River 3 has 23 outages plotted here, averaging 11 days each. The most recent, in Aug 2009, was a unplanned outage lasting 1 day.
?
Scheduled refueling outage durations over time. Green bars are at or below this unit's average, amber up to 30% above it, red beyond that. The dashed line is the average. Shorter outages mean better execution.

Refueling Duration Trend

Crystal River 3 has completed 5 scheduled refueling outages on record, averaging 35 days each. The most recent, in Nov 2007, ran 34 days.
?
Time in days from first power generation (>0%) to sustained full power (≥95% for 2+ consecutive days) after each scheduled refueling outage. The dashed line marks the average. Includes startup testing holds and power dips.

Startup Duration Trend

After a refueling outage, Crystal River 3 takes about 4 days to climb from first power back to full power. That average is drawn from 5 startups on record, and the most recent took 2 days.
?
Daily reactor power over the 120 days before each scheduled refueling outage, one line per refueling, lined up on the day the outage began. A coastdown is the slow decline as the fuel runs out near the end of a cycle. The highlighted line is the most recent refueling and fainter lines are older. Counts and medians cover coastdowns of a week or longer. A shutdown straight from full power, with no decline ahead of it, is what a forced outage looks like.

Coastdown Before Refueling

2 of 6 refuelings 23 days median 80% power at shutdown 0.5% per day
Crystal River 3 coasted down for a week or longer before 2 of its 6 refuelings on record. Those coastdowns ran a median of 23 days and ended near 80% power. The most recent refueling, in Sep 2009, began with no extended coastdown.
?
Monthly capacity factor with outage events overlaid as red bands. Green bars show average power level per month. Toggle to Daily view for raw daily data.

Power History

Over its operating life, Crystal River 3 has run at about 68.2% of its rated capacity. Across the last 12 reported months it averaged 0.0%. On the chart, green stretches near the top are full-power running, amber marks reduced power (50 to 89%), and red drops toward zero are outages.

Outage History & Daily Power Log

This table logs every recorded outage for Crystal River 3, 24 in all since 1999. Of those, 6 were scheduled refueling outages and 18 were unplanned or forced. The typical outage lasted about 67 days. Where the Scheduled column shows (Model), the date is a NukeWorker projection because the utility had not published one.
Scheduled RFO16Ext. Shutdown
2009-09-26 Decommissioned 1228 (D&D) 32d 2009-09-26 0d
Unscheduled
2009-08-25 2009-08-25 1 203d - -
Unscheduled
2009-02-03 2009-02-03 1 6d - -
Unscheduled
2009-01-28 2009-01-28 1 153d - -
Unscheduled
2008-08-25 2008-08-28 4 158d - -
Unscheduled
2008-03-02 2008-03-20 19 87d - -
Scheduled RFO15
2007-11-03 2007-12-06 34 254d 2007-11-03 0d
Unscheduled
2007-02-22 2007-02-22 1 183d - -
Unscheduled
2006-08-19 2006-08-23 5 146d - -
Unscheduled
2006-03-18 2006-03-26 9 71d - -
Unscheduled
2005-12-31 2006-01-06 7 22d - -
Scheduled RFO14
2005-10-29 2005-12-09 42 413d 2005-10-28 +1d
Unscheduled
2004-09-07 2004-09-11 5 166d - -
Unscheduled
2004-03-24 2004-03-25 2 137d - -
Unscheduled
2003-11-08 2003-11-08 1 2d - -
Unscheduled
2003-11-06 2003-11-06 1 2d - -
Scheduled RFO13
2003-10-04 2003-11-04 32 330d 2003-10-04 0d
Unscheduled
2002-11-08 2002-11-08 1 380d - -
Scheduled RFO12
2001-09-29 2001-10-24 26 121d 2001-09-29 0d
Unscheduled
2001-05-19 2001-05-31 13 246d - -
Unscheduled
2000-09-10 2000-09-15 6 135d - -
Unscheduled
2000-04-27 2000-04-28 2 151d - -
Unscheduled
1999-11-27 1999-11-28 2 17d - -
Scheduled RFO11
1999-10-01 1999-11-10 41 - 1999-10-01 0d