Salem 1

Refueling Outage · Day 21

PSEG Nuclear·Hancocks Bridge, NJ·PWR·1,153 MWe

Data refreshed 13.2h ago Rx Status: Oct 23, 2026 at 5:36 AM (M-F)

Reactor Status Timeline

Refueling Outage · Day 21 NRC data, Mon to Fri ? Actual daily reactor status from NRC reports (Mon to Fri) and the current state. What is coming -- the utility's published Scheduled outage and NukeWorker's model Projection -- is part of a subscription. Colored by status. How far ahead you can see depends on your plan.
Nov2025DecJan2026FebMarAprMayJunJulAugSepOctNovOnline: Oct 24, 2025 to Feb 22, 2026Reduced Power: Feb 23, 2026Online: Feb 24, 2026 to Oct 3, 2026Refueling Outage (1R31): Oct 4, 2026 to Oct 24, 20261R31Today
OnlineReduced PowerRefueling Outage
?
Composite Operational Excellence Score (0-100) — average percentile rank across 7 dimensions in three sub-scores: Reliability (capacity factor, forced outage days, B2B avg streak), Efficiency (fuel utilization, refuel duration), and Discipline (startup duration, scram count). 5-year window. Higher = more operationally excellent. Click to see the full breakdown.
   
Excellence
Rank locked · 93 units
Subscribers
?
Days of continuous operation since the last outage ended (Started 2026-10-23). Has forced outage(s) since last refueling.
--
Current Run
offline
?
Longest recorded period of continuous operation between outages (2017-11-11 to 2019-04-13).
518
Record Run
days
?
Breaker-to-Breaker runs — continuous operation exceeding the cycle-adjusted threshold set for this unit with no trips to 0% power.
5
B2B Runs
?
Lifetime capacity factor: average power level across all recorded days (100% = always at full power).
88.7%
Capacity Factor
?
Net electricity actually generated over the most recent 12 months reported by the U.S. EIA (Form EIA-923), summed across every unit at this plant. Authoritative actuals, not an estimate.
19.28 TWh
Net Generation
EIA-923 · 12 mo to 2026-07 · plant total
?
Total number of scheduled refueling outages detected in the historical data.
19
Outages
since 1999
?
Average time from first power generation (>0%) to sustained full power (≥95% for 2+ days) across the last 3 scheduled outages. Click to compare against the fleet on the Operator Efficiency Leaderboard.
2.3
Avg Startup
days (last 3)
?
Average fuel utilization — percent of the designed fuel cycle that this unit consumes before refueling, derived from the historical burn-down trajectory. Higher = more efficient operator (refuels with less margin remaining; closer to coastdown). Computed as 100% minus the unit's average refuel-point fuel %, using the last 3 years where available, otherwise lifetime average. Click to compare against the fleet on the Operator Efficiency Leaderboard.
98.4%
Fuel Utilization
3yr avg

Reactor Status

Capacity Factor (365-Day)

?
0%
Current
94.5%
365-Day Avg
#3
of 94 plants
Min: 0% Max: 100% 21 days <80%

Outage Days by Year

?
Total days spent in outage each year, split by scheduled refueling (blue) and forced/unplanned (red). Lower totals indicate better reliability and outage execution. Hover for details.
Across its recorded history, Salem 1 has spent 780 days in scheduled refueling outages and 167 days in forced or unplanned outages. Taller bars mark the years with the most downtime.
?
Duration of each outage in days, shown chronologically. Green bars are scheduled refueling outages, red bars are forced/unscheduled. The orange dashed line marks the average duration. Extended outages (>180 days) and D&D periods are excluded.

Outage Duration Trend

Salem 1 has 53 outages plotted here, averaging 18 days each. The most recent, in Oct 2026, was a scheduled refueling outage lasting 20 days.
?
Scheduled refueling outage durations over time. Green bars are at or below this unit's average, amber up to 30% above it, red beyond that. The dashed line is the average. Shorter outages mean better execution.

Refueling Duration Trend

Salem 1 has completed 19 scheduled refueling outages on record, averaging 41 days each. The most recent, in Oct 2026, ran 20 days.
?
Time in days from first power generation (>0%) to sustained full power (≥95% for 2+ consecutive days) after each scheduled refueling outage. The dashed line marks the average. Includes startup testing holds and power dips.

Startup Duration Trend

After a refueling outage, Salem 1 takes about 4 days to climb from first power back to full power. That average is drawn from 18 startups on record, and the most recent took 2 days.
?
Daily reactor power over the 120 days before each scheduled refueling outage, one line per refueling, lined up on the day the outage began. A coastdown is the slow decline as the fuel runs out near the end of a cycle. The highlighted line is the most recent refueling and fainter lines are older. Counts and medians cover coastdowns of a week or longer. A shutdown straight from full power, with no decline ahead of it, is what a forced outage looks like.

Coastdown Before Refueling

6 of 19 refuelings 24 days median 74% power at shutdown 0.7% per day
Salem 1 coasted down for a week or longer before 6 of its 19 refuelings on record. Those coastdowns ran a median of 24 days and ended near 74% power. The most recent refueling, in Oct 2026, began with no extended coastdown.
?
Monthly capacity factor with outage events overlaid as red bands. Green bars show average power level per month. Toggle to Daily view for raw daily data.

Power History

Over its operating life, Salem 1 has run at about 88.7% of its rated capacity. Across the last 12 reported months it averaged 92.7%. On the chart, green stretches near the top are full-power running, amber marks reduced power (50 to 89%), and red drops toward zero are outages.

Outage History & Daily Power Log

This table logs every recorded outage for Salem 1, 53 in all since 1999. Of those, 19 were scheduled refueling outages and 34 were unplanned or forced. The typical outage lasted about 18 days. Where the Scheduled column shows (Model), the date is a NukeWorker projection because the utility had not published one.
Scheduled 1R31
2026-10-04 In Outage 20+ 492d 2026-10-04 0d
Scheduled 1R30
2025-04-13 2025-05-30 48 85d 2025-04-02 +11d
Unscheduled
2025-01-17 2025-01-18 2 433d - -
Scheduled 1R29
2023-10-08 2023-11-11 35 508d 2023-10-07 +1d
Scheduled 1R28
2022-04-09 2022-05-18 40 478d 2022-04-09 0d
Unscheduled
2020-12-16 2020-12-17 2 3d - -
Scheduled 1R27SGR/Major
2020-10-03 2020-12-13 72 192d 2020-10-20 -17d
Unscheduled
2020-02-26 2020-03-25 29 253d - -
Scheduled 1R26
2019-04-13 2019-06-18 67 518d 2019-04-16 -3d
Scheduled 1R25
2017-10-13 2017-11-11 30 225d 2017-10-13 0d
Unscheduled
2017-03-01 2017-03-02 2 215d - -
Scheduled 1R24SGR/Major
2016-04-15 2016-07-29 106 391d 2016-04-14 +1d
Unscheduled
2015-03-16 2015-03-21 6 115d - -
Scheduled # 50550 Manual 1R23
2014-10-20 2014-11-21 33 163d 2014-10-19 +1d
Scram # 50092 Auto
2014-05-08 2014-05-10 3 21d - -
Scram # 50032 Auto
2014-04-14 2014-04-17 4 5d - -
Scram # 50012 Manual
2014-04-09 2014-04-09 1 228d - -
Unscheduled
2013-08-23 2013-08-24 2 93d - -
Scheduled 1R22
2013-04-15 2013-05-22 38 165d 2013-04-14 +1d
Scram # 48457 Manual
2012-10-30 2012-11-01 3 177d - -
Scram # 47874 Auto
2012-05-01 2012-05-06 6 165d - -
Scheduled 1R21
2011-10-24 2011-11-18 26 185d 2011-10-22 +2d
Scram # 46774 Manual
2011-04-22 2011-04-22 1 188d - -
Unscheduled
2010-10-16 2010-10-16 1 85d - -
Unscheduled
2010-07-08 2010-07-23 16 72d - -
Scheduled 1R20
2010-04-04 2010-04-27 24 508d 2010-04-07 -3d
Scheduled 1R19
2008-10-15 2008-11-12 29 288d 2008-10-15 0d
Unscheduled
2007-12-29 2008-01-01 4 241d - -
Unscheduled
2007-05-01 2007-05-02 2 6d - -
Unscheduled Startup Hold
2007-04-25 2007-04-25 1 8d - -
Scheduled 1R18
2007-03-28 2007-04-17 21 384d 2007-03-27 +1d
Unscheduled
2006-03-09 2006-03-09 1 125d - -
Scheduled 1R17
2005-10-12 2005-11-04 24 174d 2005-10-11 +1d
Unscheduled
2005-04-20 2005-04-21 2 125d - -
Unscheduled
2004-12-04 2004-12-16 13 68d - -
Unscheduled
2004-09-25 2004-09-27 3 114d - -
Unscheduled
2004-06-03 2004-06-03 1 5d - -
Scheduled 1R16
2004-03-31 2004-05-29 60 165d 2004-03-30 +1d
Unscheduled
2003-10-16 2003-10-18 3 21d - -
Unscheduled
2003-09-20 2003-09-25 6 50d - -
Unscheduled
2003-07-30 2003-08-01 3 266d - -
Scheduled 1R15
2002-10-11 2002-11-06 27 213d 2002-10-11 0d
Unscheduled
2002-03-06 2002-03-12 7 142d - -
Unscheduled
2001-09-25 2001-10-15 21 124d - -
Unscheduled
2001-05-23 2001-05-24 2 6d - -
Scheduled 1R14
2001-04-06 2001-05-17 42 118d 2001-04-06 0d
Unscheduled
2000-12-09 2000-12-09 1 120d - -
Unscheduled
2000-08-10 2000-08-11 2 117d - -
Unscheduled
2000-04-13 2000-04-15 3 91d - -
Unscheduled
2000-01-07 2000-01-13 7 74d - -
Scheduled 1R13
1999-09-18 1999-10-25 38 118d 1999-09-18 0d
Unscheduled
1999-05-21 1999-05-23 3 79d - -
Unscheduled
1999-02-28 1999-03-03 4 - - -